Centrus Energy Corp. shipped the first newly built centrifuge for its Piketon, Ohio uranium enrichment plant out of its Technology and Manufacturing Center in Oak Ridge, Tennessee, on Oct. 29, 2026, in an event attended by government officials. The shipment is the first unit of a manufacturing program that company executives describe at a very different scale from the existing demonstration cascade.

A Build-Out Measured in Thousands

Centrus SVP Patrick Brown said one machine would be filled that day at Piketon, with 11,519 more still to come — implying a finished plant of roughly 11,520 centrifuges. That figure is orders of magnitude beyond the 16-machine cascade Centrus has operated in Ohio since late 2023, and it frames the Piketon expansion as an industrial program rather than a pilot.

The first machine left Oak Ridge ahead of the company's previously announced year-end target. Centrus also said it had completed its first certified-for-construction package for the Piketon expansion, a procedural milestone that allows construction work to move forward under the plant's licensing basis.

Oak Ridge Restart Underpins the Schedule

Centrus restarted centrifuge manufacturing at Oak Ridge in December 2025, reviving a capability that had been dormant. In January 2026 the company announced a $560 million investment to develop and modernize the Oak Ridge Technology and Manufacturing Center for high-rate manufacturing.

The strategic logic is straightforward: centrifuge availability, not demand, has been the binding constraint on Western HALEU supply. Russia and China hold the only commercial-scale HALEU production infrastructure globally, and Western restrictions on Russian nuclear materials have sharpened the case for domestic capacity.

What Comes Next

The Piketon build-out is expected to begin producing in the 2029 timeframe under a Department of Energy HALEU task order, with additional capacity layered on afterward. Each centrifuge that leaves Oak Ridge is therefore a leading indicator for how quickly U.S. HALEU supply moves from demonstration volumes to reactor-scale commitments.

For advanced reactor developers holding Centrus agreements, the Piketon schedule is now the reference point against which fuel delivery timelines will be judged.