Centrus Energy's contingent backlog — sales tied to new capacity at its Piketon, Ohio, site — jumped from $3 billion in early August to $5.4 billion by the end of September, as reactor developers lined up for HALEU and low-enriched uranium.

Demonstration cascade to full capacity

Centrus currently produces HALEU across one 16-machine demonstration cascade that produced about 900 kilograms a year for the Department of Energy. Its next full cascade of new centrifuges is expected to come online in 2029, and the base-case build-out targets 12 metric tons of HALEU a year. The timeline for reaching 12 metric tons per year remains unclear.

The DOE is owed one ton of HALEU by March 2032 under its $900 million contract. Centrus's Piketon site also has to make LEU, and its Russian and French supply contracts — which cover most of what its LEU business sells today — run out at the end of 2027 and 2030.

Customer queue

Centrus's customer slide lists initial loads of 5 tons for an Aurora core, 1.5 tons per Xe-100, 1 ton for Antares and about 15 tons for Natrium, totalling 22.5 tons — nearly two years of full base-case capacity. The count includes just one Aurora and one Xe-100, while Oklo's deal covers up to five Aurora powerhouses, Dow's Long Mott plant alone has four Xe-100s, and Radiant's volume is undisclosed.

Since August, Centrus signed three more definitive deals for future output, all with prepayments: X-energy on 6 August for LEU and HALEU for its first Xe-100 reactors and TRISO-X fuel; Radiant on 9 September for HALEU for multiple Kaleidos microreactors with deliveries before the end of the decade; and Antares on 17 September for "unobligated" HALEU that can support national security missions, also due before the end of the decade.

Centrus's investor deck counts TerraPower's Natrium reactor under a 2023 MOU, with planned deployment in 2030. On the Q3 call, CEO Amir Vexler touted the "flexibility to use planned HALEU capacity for various assays of LEU and LEU plus if needed." Asked if Centrus would pull capacity forward, he said "there is really no changes in terms of the cadence that we are planning in terms of rolling out our capacity."