A European first in uranium density
Framatome's CERCA manufacturing facility in Romans-sur-Isère, France has produced the first depleted-uranium fuel plates for the conversion of the Technical University of Munich's FRM-II research reactor from high-enriched uranium above 95% uranium-235 to HALEU below 20%. The two plates were fabricated at final dimensions using uranium-molybdenum monolithic fuel, described as achieving the highest uranium fuel density ever realised in Europe.
The plates are not intended for reactor use. They are a manufacturing qualification step — validating the industrial processes developed with TUM — and mark a milestone toward converting the 20 MWt FRM-II, which has operated since 2005 as a high-flux neutron source for science and medical radioisotope production.
Why monolithic fuel matters
Most research reactors built up to the late 1970s were designed for HEU fuel above 20% uranium-235, some as high as 93%. Since the late 1970s, international efforts have focused on converting them to fuel enriched to no more than 20%, and many have already been converted. Specialised high-performance reactors such as FRM-II are harder: they need higher uranium density to preserve their neutron flux at lower enrichment.
Monolithic U-Mo fuel — essentially pure metal with about 10% molybdenum, rather than a U-Mo dispersion in aluminium — is the answer being developed. Framatome completed development of the main component of the monolithic U-Mo fuel in 2023; its high uranium density is what allows the reactor to perform as intended below 20% enrichment.
Next step: a HALEU test assembly
The next phase will be fabrication of a Generic Test Assembly with monolithic U-Mo plates incorporating actual HALEU material, with irradiation testing scheduled for 2028. FRM-II Reactor Conversion Programme Director Christian Reiter said the first two depleted-uranium plates at final dimensions give a strong basis for the next development and qualification steps.
Qualification of a new research reactor fuel is a multi-year irradiation and post-irradiation examination process, not a single manufacturing milestone.
Funding and timeline
TUM has collaborated with Framatome since 2019; a 2024 cooperation agreement aimed to industrialise production of U-Mo monolithic fuel containing less than 20% uranium-235. The programme is funded by the Free State of Bavaria through TUM under a direct contract with Framatome, and is also supported by the European Commission and Euratom through several projects, including the EUR 12.8 million (USD 13.3 million) EU-CONVERSION project launched in early 2025.