The U.S. Nuclear Regulatory Commission has approved a construction permit for Dow and X-energy's proposed Long Mott Generating Station at Dow's Seadrift Operations site in Texas, according to the U.S. Department of Energy's Office of Nuclear Energy. The decision, dated November 9, 2026, marks the first advanced nuclear facility authorized for construction at a U.S. industrial site.
Why the permit matters for HALEU demand
The Long Mott project would deploy four X-energy Xe-100 small modular reactors. Each Xe-100 produces 80 MWe or 200 MWth, and the four-unit plant could provide up to 320 MWe while supporting industrial steam needs for 60 years. The Xe-100 is a high-temperature gas-cooled reactor that uses TRISO-X fuel, a tri-structural isotropic coated particle fuel made with high-assay low-enriched uranium.
The NRC approval is also the first construction permit for a high-temperature gas-cooled reactor in more than 50 years and the first-ever NRC approval for a pebble-bed core design. That regulatory first matters beyond this single project: it creates a licensing precedent for pebble-bed HALEU reactors and for industrial customers seeking reliable, high-temperature process heat.
Industrial siting and DOE support
The project is supported by DOE's Advanced Reactor Demonstration Program, which aims to accelerate commercial deployment of advanced nuclear technologies. DOE has supported decades of research and development on high-temperature gas-cooled reactors and TRISO fuel technologies, helping establish the technical foundation for today's designs.
The permit allows X-energy and Dow to advance toward construction readiness, including finalizing the Xe-100 design, strengthening the supply chain for long-lead components, and preparing an operating license application for NRC review.
The project is targeting initial energy delivery in the early 2030s. For the HALEU market, Long Mott is a concrete demand signal: four reactors requiring TRISO-X pebbles, backed by a licensed fuel fabrication route and an industrial offtaker. It also shows how advanced reactors can be paired with manufacturing operations that need both electricity and high-temperature steam.