Oklo and Centrus Energy have finalized multiple multi-year agreements to supply high-assay low-enriched uranium (HALEU) for Oklo's advanced reactor projects, converting a developer's fleet ambitions into a fuel demand signal with a date attached.

Scope of the agreements

The fuel covered is intended to support up to five Aurora powerhouses over multiple years. Deliveries from Centrus's American Centrifuge Plant in Piketon, Ohio, are expected to begin in 2029.

The arrangement also supports Oklo's planned Ohio nuclear power campus, which targets data centers and other energy-intensive operations. That pairing matters: data-center load growth is one of the few demand segments willing to sign long-term power contracts years before a first-of-a-kind reactor is operating.

Why the 2029 date carries weight

The supply schedule is pinned to a plant that has not yet begun commercial HALEU output. According to the US Department of Energy, US suppliers currently have no commercial production of HALEU, defined as uranium enriched to 5% to 20% uranium-235. Centrus, which received $900 million in federal funding for domestic enrichment as part of a $2.7 billion government allocation, expects to produce new HALEU at its Ohio facility in 2029.

That means the Oklo agreements and the Centrus build-out are now on the same timeline. Any slippage in the enrichment plant propagates directly into Oklo's fuel delivery plan, and from there into the operating dates of the Aurora units the fuel is meant to serve.

The agreements illustrate a broader pattern in which reactor developers secure fuel years before planned commercial operations.

Fuel-first contracting becomes the norm

Historically, fuel contracts followed reactor construction. Advanced reactor developers are inverting that order because HALEU is scarce and because a credible fuel supply is now part of what lenders, regulators and customers want to see. Advance payments under such agreements can also help suppliers finance production capacity, sharing the capital burden between buyer and enricher.

What to watch

The open questions are volume and price. Neither company disclosed how much separative work or how many kilograms of HALEU the multi-year agreements cover, nor how the fuel will be converted and fabricated before it reaches an Aurora unit. Confirmation that Centrus has started commercial HALEU production at Piketon will be the decisive milestone for the 2029 delivery schedule.

This article was assisted by AI analysis. Please refer to the original source for official information.