The HALEU that Urenco has committed to Blykalla will come from a plant that does not yet exist. Urenco will enrich the material at its Advanced Fuels Facility in Capenhurst, England, a project planned to begin operations in 2031, with first deliveries of enriched uranium to the Swedish reactor developer expected in the early 2030s.

The numbers behind the plant

The Capenhurst HALEU project involves an investment of approximately 400 million pounds sterling and an initial capacity of up to 27 metric tonnes per year. That figure is the clearest public benchmark yet for the scale of Western HALEU enrichment capacity outside the United States.

The commercial agreement itself was signed on 12 November in London and announced on 16 November 2026, with Urenco supplying enrichment services and Blykalla providing the uranium feed.

Why the timeline is the story

HALEU demand from advanced reactor developers is being booked now, but the capacity to serve it arrives later in the decade. The gap between contract signature and first delivery — roughly five to seven years in this case — defines the fuel risk that first-of-a-kind reactor projects must manage. It also explains why developers are signing enrichment agreements years before their reactors approach construction.

Urenco's Capenhurst facility is planned to start operations in 2031, with first deliveries of enriched uranium to Blykalla expected in the early 2030s.

A European pillar in a two-region supply chain

The Capenhurst project gives Europe an indigenous HALEU enrichment route to sit alongside Urenco's US operations in Eunice, New Mexico, which have already begun producing commercial material in the low end of the HALEU range. For European advanced reactor developers, that matters: a domestic enrichment option reduces exposure to transatlantic logistics and to the policy risk attached to moving material enriched above 5% uranium-235.

Urenco has not disclosed how much of the 27-tonne initial capacity is committed to Blykalla, nor the enrichment level to be produced for the SEALER programme. Both details will shape how much room remains for other European developers seeking HALEU offtake in the 2030s.

This article was assisted by AI analysis. Please refer to the original source for official information.